Public-record permit data only — not zoning, feasibility, or legal advice. Records may be incomplete, delayed, or mis-categorized. Check with your city planning department.
About this data
  • Neighborhood pages cover 2020 onward: City of Los Angeles Department of Building and Safety permits in this neighborhood's Neighborhood Council area, which may not match every local definition of the neighborhood. Build type is classified automatically from permit descriptions.
  • Costs are declared permit valuations (single-ADU permits only), not final construction costs.

Permits by year

20209
202118
202230
202341
202435
202538
2026 so far33
Permits by year and type (table)
YearAll ADU permitsGarage conversionsDetached
2020922
20211867
2022301311
2023411018
2024351017
202538918
2026 so far33618

“—” means the source for that year does not report ADU type.

Read more: ADU types explained

Not counted: 3 expired or cancelled permits.

How South Central compares

ADU rules

Los Angeles' ADU rules apply citywide, with extra rules for hillside, fire-zone and coastal lots: see the rules table.

How long permits take

TypeMedian days, application to permitMiddle halfPermits
Detached ADU250156 – 37890
Attached ADU20198 – 41643
Garage conversion12973 – 30054
Junior ADU (JADU)too few to say1
Unclassified251194 – 53011

Middle half: the range covering the middle 50% of permits (a quarter were lower, a quarter higher).

Read more: How long ADU permits take in Los Angeles (and other cities) · How long ADUs take to build

What happened to these permits

Of the 101 ADU permits issued in South Central from 2020 through 2023, including ones that later expired or were cancelled, 74% have been signed off by the city as finished. Where the certificate of occupancy date is recorded, it came a median of 17 months after the permit.

What became of the permitShare
Finished (signed off by the city)74%
Still open20%
Expired or cancelled3%
Closed or other status3%

Expired and cancelled permits aren't in this page's totals; they're included here so the table covers every permit issued. A still-open permit may be under construction or stalled.

What neighbors declared as cost

TypeMedian declared valueMiddle halfPermits
Detached ADU$120,000$87,500 – $143,90051
Attached ADU$50,000$28,150 – $105,00027
Garage conversion$50,000$30,000 – $75,00053
Junior ADU (JADU)too few to say1
Unclassifiedtoo few to say6

Declared permit valuations often understate real construction cost.

Read more: What ADUs cost in Los Angeles

Read more: How to choose an ADU builder

An ADU builder serving Los Angeles? Feature your business on this page.

Recent ADU permits in South Central

Street names only. See each permit on the map.

Questions about ADUs in South Central

How many ADUs have been permitted in South Central?

The City of Los Angeles issued 204 permits for ADUs in South Central from 2020 through Oct 31, 2026, including 56 garage conversions and 91 detached ADUs.

How long does an ADU permit take in South Central?

From application to issued permit, the median in South Central was 129 days for garage conversions and 250 days for detached ADUs.

How much does an ADU cost in South Central?

The median value declared on permits was $50,000 for garage conversions and $120,000 for detached ADUs. Declared permit values often understate the full construction cost, so get several builder quotes.

How long does it take to build an ADU in South Central?

Of the 101 ADU permits issued in South Central from 2020 through 2023, including ones that later expired or were cancelled, 74% have been signed off by the city as finished. Where the certificate of occupancy date is recorded, it came a median of 17 months after the permit.

Can I build an ADU on my property in South Central?

California law allows ADUs on most residential lots with a house, but what you can build depends on your lot, zoning and hillside or fire-zone rules. This site shows permits, not eligibility; check with the Los Angeles Department of Building and Safety or a licensed builder.

How current is this?

How our data works · Download the data · Free to reuse with credit to SoCal ADU Tracker (socaladutracker.com), under CC BY 4.0.