The short answer

For ADU permits the City of Los Angeles issued in 2025, the median time from application to issued permit was 103 days for garage conversions, 72 days for junior ADUs, 135 days for attached ADUs and 158 days for detached ADUs. Half of permits were faster than that and half slower.

The middle half of permits took: garage conversions 50–215 days, junior ADUs 37–141 days, attached ADUs 72–268 days and detached ADUs 90–301 days.

Is it getting faster?

Detached ADUs issued in 2025 took a median of 158 days, down from 254 for those issued in 2022. Garage conversions issued in 2025 took a median of 103 days, down from 147 for those issued in 2021.

Median days, application to permit202020212022202320242025
Garage conversion101147138138135103
Junior ADU (JADU)94132110716872
Attached ADU118192207205180135
Detached ADU194247254231201158

By the year the permit was issued. Applications open more than three years are left out.

What about the state's 60-day rule?

California law requires a city to approve or deny a complete ADU application within 60 days (Government Code § 66317, summarized in the state's ADU Handbook). The times above run from the day an application was first submitted to the day the permit was issued, so they also include plan-check corrections, resubmittals and paying fees. That is why most take longer than 60 days. Los Angeles also offers pre-approved standard ADU plans, which the city says shorten plan check; see how pre-approved ADU plans work.

It depends on the neighborhood

Across the San Fernando Valley's Los Angeles neighborhoods (all ADU types, 2020 to date), the fastest medians were in West Hills (83 days), Canoga Park (101 days) and Winnetka (103 days); the slowest were in Shadow Hills and Lake View Terrace (173 days), Toluca Lake (164 days) and Studio City (159 days). Hillside and fire-zone areas tend to take longer. Each neighborhood page has its own breakdown.

Other cities

Outside Los Angeles, the figures come from the application and permit dates cities report to the state. Some cities report their planning application date, so their times include planning review; see each city's page.

CityMedian days, application to permitPermits timed
Alhambra230397
Baldwin Park310134
Burbank276794
Calabasas21856
Camarillo80104
Culver City147357
Downey173741
El Monte415151
Glendale1481,051
Lakewood145292
Lancaster17233
Long Beach1652,381
Moorpark8076
Norwalk204334
Ojai5867
Oxnard428259
Pasadena249622
Port Hueneme3616
Rosemead300372
San Fernando43307
Santa Monica335260
Simi Valley21180
Temple City258140
Thousand Oaks146266
Torrance190603
Unincorporated Los Angeles County3013,597
Unincorporated Ventura County22153
Whittier209391

After the permit: building it

Of the 21,796 ADU permits issued in Los Angeles from 2020 through 2023, including ones that later expired or were cancelled, 82% have been signed off by the city as finished. Where the certificate of occupancy date is recorded, it came a median of 14 months after the permit.

Search your address on the map →

General information, not legal, zoning or financial advice. Rules change and depend on your lot; check with your city before you design or build.