The short answer

For ADU permits the City of Los Angeles issued from 2020 through 2023, the median time from issued permit to the city's final sign-off (certificate of occupancy) was about 13 months for garage conversions, about 11 months for junior ADUs, about 15 months for attached ADUs and about 16 months for detached ADUs. Add the permit itself (see how long permits take) for the whole timeline.

TypeMedian months, permit to sign-offSigned off as finishedPermits
Garage conversion1382%10,670
Junior ADU (JADU)1183%1,531
Attached ADU1582%2,759
Detached ADU1682%5,748

“Signed off as finished” counts every permit issued in those years, including ones that later expired or were cancelled. Months use permits with a recorded certificate of occupancy date.

By the year the permit was issued

Median months to sign-off2020202120222023
Garage conversion12131312
Junior ADU (JADU)11131210
Attached ADU13141515
Detached ADU15161615

Recent years only include projects already finished, so they can look faster than they will end up.

What happens after the permit

Once the permit is issued, the builder schedules inspections at each stage (foundation, framing, utilities, final). The city signs the unit off as finished with a certificate of occupancy after the final inspection; only then can it be lived in or rented. Garage conversions and junior ADUs reuse an existing structure, which is why they tend to finish sooner than a new detached building.

It depends on the neighborhood

Across the San Fernando Valley's Los Angeles neighborhoods (all ADU types), the quickest median builds were in Reseda (10 months), West Hills (11 months) and Winnetka (11 months); the longest were in Shadow Hills and Lake View Terrace (16 months), North Hollywood (15 months) and Valley Glen (14 months).

Other cities

From the permit and completion dates cities report to the state, for permits issued in the same years (2020 through 2023, except the incomplete years noted below).

City or areaMedian months, permit to completionProjects timed
Alhambra13256
Anaheim10507
Baldwin Park11142
Brea831
Buena Park856
Calabasas1312
Camarillo634
Carlsbad11220
Chula Vista12293
Costa Mesa1292
Culver City8109
Cypress924
Dana Point1326
Del Mar1558
Downey9256
El Cajon10127
El Monte1463
Encinitas10358
Escondido10173
Fountain Valley8165
Fullerton12209
Garden Grove9954
Glendale10837
La Habra963
La Mesa10168
Laguna Beach11135
Laguna Niguel1119
Lake Forest1135
Lakewood8287
Lancaster14203
Lemon Grove1220
Long Beach101,533
Mission Viejo1026
Moorpark1053
National City1442
Newport Beach1367
Norwalk622
Oceanside9331
Ojai551
Orange8115
Oxnard10230
Pasadena9132
Placentia834
Poway1273
Rosemead12225
San Clemente1064
San Fernando6125
San Juan Capistrano1024
San Marcos863
Santa Ana10422
Santa Monica1353
Santee1027
Solana Beach1245
Stanton987
Temple City1823
Thousand Oaks576
Torrance14279
Tustin723
Unincorporated Los Angeles County131,681
Unincorporated Orange County11131
Unincorporated San Diego County12941
Unincorporated Ventura County12123
Vista691
Westminster7358
Whittier9174
Yorba Linda1140

Same-day “completions” (the permit date reported twice) are left out: 2 in Buena Park, 3 in Carlsbad, 2 in Culver City, 1 in Del Mar, 2 in Encinitas, 2 in Garden Grove, 1 in Glendale, 4 in La Habra, 2 in La Mesa, 1 in Laguna Beach, 1 in Lakewood, 4 in Long Beach, 1 in Newport Beach, 1 in Oceanside, 6 in Ojai, 1 in Pasadena, 1 in Poway, 1 in San Fernando, 1 in Santa Ana, 2 in Unincorporated Los Angeles County, 37 in Unincorporated Ventura County, 30 in Vista, 1 in Whittier and 10 in Yorba Linda.

Years with incomplete reports are left out: 2020 in Cypress, 2021 in Ojai and 2021 in Unincorporated Orange County.

Left out: Burbank, whose reports give the same date for the permit and the completion, so build time can't be measured.

Search your address on the map →

General information, not legal, zoning or financial advice. Rules change and depend on your lot; check with your city before you design or build.