In short

Public-record permit data only — not zoning, feasibility, or legal advice. Records may be incomplete, delayed, or mis-categorized. Check with your city planning department.
About this data
  • Source: California HCD Housing Element Annual Progress Reports. The state data does not say whether an ADU is detached, attached, a garage conversion or a JADU, so most records show as 'unknown'. Permit valuations are not published in this source. Timelines use the application date the city reported to the state, matched to the permit where possible; some cities report their planning application date, so timelines can include planning review. Each project is counted once, in its building-permit year (or completion year when no permit date was reported).

Permits by year

201813
201939
202040
202180
2022125
2023128
2024121
202587
Permits by year and type (table)
YearAll ADU permitsGarage conversionsDetached
201813——
201939——
202040——
202180——
2022125——
2023128——
2024121——
202587——

“—” means the source for that year does not report ADU type.

Read more: ADU types explained

ADU rules in Torrance

State law check: HCD found the 2022 ordinance noncompliant (September 5, 2024), including its one-ADU limit and deed restriction; the city rewrote it (Ord. 3954, August 19, 2025). We haven't seen HCD's review of the new ordinance.

RuleTorrance's codeState law guarantees
Maximum size1,000 sq ft, attached or detached. State-law detached ADU 800 sq ft. Junior ADU 500 sq ft.At least 850 sq ft (1,000 sq ft with 2+ bedrooms) must be allowed; an 800 sq ft detached ADU always is. Conversions of existing space have no size cap. Junior ADU: up to 500 sq ft.
HeightDetached: 18 ft (1 story) or 23 ft (2 stories). Attached: 18 ft (1 story) or 25 ft (2 stories). Hillside Overlay and Coastal Zone: detached 16 ft, one story.Detached: at least 16 ft (18 ft within ½ mile of transit, plus 2 ft for a matching roof). Attached: 25 ft or the zone's limit, whichever is lower.
Setbacks4 ft side and rear (attached: the house's rear setback); detached 15 ft front; 6 ft between buildings. None for conversions.No more than 4 ft side and rear; none for conversions of existing space.
Parking1 space per ADU (tandem on the driveway is fine) unless exempt (transit, conversions, car share and others); no replacement parking.At most 1 space; none within ½ mile of transit and in several other cases. No replacement parking when a garage is converted.
Owner living on siteNone for ADUs. Junior ADU: the owner lives in the house or the junior ADU, with a recorded covenant.None for ADUs. A junior ADU that shares a bathroom with the house requires the owner to live in one of them.
How many on a single-family lotOne converted ADU, one new detached ADU (800 sq ft) and one junior ADU.One ADU converted from existing space, one junior ADU and one new detached ADU (up to 800 sq ft). From January 1, 2027: two new detached ADUs (a city then needn't allow a junior ADU on that lot).
Short-term rentalsNot for less than 30 days, for ADUs and junior ADUs.No guarantee: cities may require rentals of more than 30 days, and junior ADUs can't be short-term rentals.

Where local rules conflict with state law, state law controls. Sources: Torrance Municipal Code § 92.2.10 (Ord. 3954, Aug 19, 2025) · Ord. 3954 second reading (Aug 19, 2025) · HCD findings (Sep 5, 2024) · HCD findings (Dec 13, 2021); HCD's list of review letters; California ADU rules. Verified Sep 30, 2026. Rules change and every lot is different: confirm with the city before you design.

How long permits take

TypeMedian days, application to permitMiddle halfPermits
Unclassified190126 – 304603

Middle half: the range covering the middle 50% of permits (a quarter were lower, a quarter higher).

Read more: How long ADU permits take in Los Angeles (and other cities) · How long ADUs take to build

From permit to completion

Of the 373 ADU permits Torrance reported issuing from 2020 through 2023, 279 (75%) have a completion reported to the state. For those, the median time from permit to completion was 14 months.

The state reports don't record expired or cancelled permits, and a completion the city hasn't reported looks the same as an unfinished project, so the share is a floor. Years with incomplete reports are left out.

What neighbors declared as cost

Cost data (declared permit valuations) is not published for this area in these sources.

Read more: How to choose an ADU builder

An ADU builder serving Torrance? Feature your business on this page.

Questions about ADUs in Torrance

How many ADUs have been permitted in Torrance?

Public records show 633 ADU permits in Torrance from 2018 through 2025. 87 in 2025, down 28% from 2024. These counts come from the city's reports to the state, which place a project in its completion year when no permit date was reported.

How long does an ADU permit take in Torrance?

Among the 603 ADU permits in Torrance with both dates recorded, half were issued within 190 days of the application; the middle half took 126 to 304 days. That includes plan-check corrections and resubmittals, not just the review itself.

Can I build an ADU on my property in Torrance?

California law allows ADUs on most lots with a house, including in Torrance, but what you can build depends on your lot, local rules and utilities. This site shows permits, not eligibility. See California ADU rules.

Where do I apply for an ADU permit in Torrance?

Apply with the City of Torrance's Building & Safety Division, which reviews ADUs through the building permit and posts pre-approved ADU plans. Official ADU page.

How current is this?

How our data works · Download the data · Free to reuse with credit to SoCal ADU Tracker (socaladutracker.com), under CC BY 4.0.