In short

Public-record permit data only — not zoning, feasibility, or legal advice. Records may be incomplete, delayed, or mis-categorized. Check with your city planning department.
About this data
  • Source: California HCD Housing Element Annual Progress Reports. The state data does not say whether an ADU is detached, attached, a garage conversion or a JADU, so most records show as 'unknown'. Permit valuations are not published in this source. Timelines use the application date the city reported to the state, matched to the permit where possible; some cities report their planning application date, so timelines can include planning review. Each project is counted once, in its building-permit year (or completion year when no permit date was reported).

Permits by year

20186
20199
202019
202145
202256
202368
202497
202599
Permits by year and type (table)
YearAll ADU permitsGarage conversionsDetached
20186——
20199——
202019——
202145——
20225600
202368——
202497——
202599——

“—” means the source for that year does not report ADU type.

Read more: ADU types explained

ADU rules in Costa Mesa

State law check: HCD found the city's 2023 ADU ordinance out of line with state law (September 11, 2024); the city amended its ADU rules April 1 and October 21, 2025, and no HCD letter on the new version is on file.

RuleCosta Mesa's codeState law guarantees
Maximum sizeDetached: 1,200 sq ft. Attached: 50% of the house or 1,000 sq ft, whichever is greater. No cap for conversions. Minimum 150 sq ft. Junior ADU 500 sq ft.At least 850 sq ft (1,000 sq ft with 2+ bedrooms) must be allowed; an 800 sq ft detached ADU always is. Conversions of existing space have no size cap. Junior ADU: up to 500 sq ft.
HeightUp to 27 ft and 2 stories, but only on the ground floor unless second-story rules are met (25 ft from the front lot line, interior or screened stairs, window limits). State-law detached ADU: 18 ft, plus 2 ft for roof pitch.Detached: at least 16 ft (18 ft within ½ mile of transit, plus 2 ft for a matching roof). Attached: 25 ft or the zone's limit, whichever is lower.
Setbacks4 ft side and rear; front setback matches the zone. 6 ft between a detached ADU and other buildings. None for conversions.No more than 4 ft side and rear; none for conversions of existing space.
ParkingNone required: parking is optional, and a space an owner adds can be tandem on the driveway or in a setback. No replacement parking for converted garages.At most 1 space; none within ½ mile of transit and in several other cases. No replacement parking when a garage is converted.
Owner living on siteNone for ADUs. Junior ADU: the owner lives in the house or the junior ADU, with a recorded covenant.None for ADUs. A junior ADU that shares a bathroom with the house requires the owner to live in one of them.
How many on a single-family lotOne converted ADU, one new detached ADU and one junior ADU on a single-family lot.One ADU converted from existing space, one junior ADU and one new detached ADU (up to 800 sq ft). From January 1, 2027: two new detached ADUs (a city then needn't allow a junior ADU on that lot).
Short-term rentals31 days or more, for ADUs and junior ADUs.No guarantee: cities may require rentals of more than 30 days, and junior ADUs can't be short-term rentals.

Where local rules conflict with state law, state law controls. Sources: Costa Mesa Municipal Code 13-35 · HCD findings (September 11, 2024) · City of Costa Mesa ADU page; HCD's list of review letters; California ADU rules. Verified Oct 5, 2026. Rules change and every lot is different: confirm with the city before you design.

How long permits take

TypeMedian days, application to permitMiddle halfPermits
Junior ADU (JADU)not reported
Unclassified195105 – 334329

Middle half: the range covering the middle 50% of permits (a quarter were lower, a quarter higher).

Read more: How long ADUs take to build

From permit to completion

Of the 185 ADU permits Costa Mesa reported issuing from 2020 through 2023, 92 (50%) have a completion reported to the state. For those, the median time from permit to completion was 12 months.

The state reports don't record expired or cancelled permits, and a completion the city hasn't reported looks the same as an unfinished project, so the share is a floor. Years with incomplete reports are left out.

What neighbors declared as cost

Cost data (declared permit valuations) is not published for this area in these sources.

Read more: How to choose an ADU builder

An ADU builder serving Costa Mesa? Feature your business on this page.

Questions about ADUs in Costa Mesa

How many ADUs have been permitted in Costa Mesa?

Public records show 399 ADU permits in Costa Mesa through 2025, nearly all since 2020. 99 in 2025, up 2% from 2024. These counts come from the city's reports to the state, which place a project in its completion year when no permit date was reported.

How long does an ADU permit take in Costa Mesa?

Among the 329 ADU permits in Costa Mesa with both dates recorded, half were issued within 195 days of the application; the middle half took 105 to 334 days. That includes plan-check corrections and resubmittals, not just the review itself.

Can I build an ADU on my property in Costa Mesa?

California law allows ADUs on most lots with a house, including in Costa Mesa, but what you can build depends on your lot, local rules and utilities. This site shows permits, not eligibility. See California ADU rules.

Where do I apply for an ADU permit in Costa Mesa?