  • Neighborhood pages cover 2018 onward: City of San Diego Development Services Department permits located in this community planning area, the city's official neighborhood boundaries, which may not match every local definition of the neighborhood. Build type is classified automatically from permit descriptions.
  • Costs are declared permit valuations (single-ADU permits only), not final construction costs.
  • The city closes a permit both after its final inspection and after it expires, and its data doesn't say which, so this page doesn't estimate how many permits were finished. Closed permits stay in the counts.

Permits by year

20189
201932
202033
202143
202256
202371
2024108
202587
2026 so far88
Permits by year and type (table)
YearAll ADU permitsGarage conversionsDetached
2018903
2019321210
202033513
2021431018
2022561220
2023711329
20241082537
2025872022
2026 so far881016

“—” means the source for that year does not report ADU type.

Read more: ADU types explained

Not counted: 61 expired or cancelled permits.

How Southeastern San Diego compares

ADU rules

San Diego's ADU rules apply citywide, with extra rules in the Coastal Zone and in very high fire hazard areas: see the rules table.

How long permits take

TypeMedian days, application to permitMiddle halfPermits
Detached ADU256156 – 415168
Attached ADU274155 – 47968
Garage conversion266157 – 396107
Junior ADU (JADU)too few to say8
Unclassified311240 – 510173

Middle half: the range covering the middle 50% of permits (a quarter were lower, a quarter higher).

Read more: How long ADUs take to build

What neighbors declared as cost

TypeMedian declared valueMiddle halfPermits
Detached ADU$119,092$85,053 – $151,085120
Attached ADU$74,777$54,738 – $121,18050
Garage conversion$59,004$40,012 – $76,38683
Junior ADU (JADU)too few to say7
Unclassified$96,751$61,248 – $181,19868

Declared permit valuations often understate real construction cost.

Read more: How to choose an ADU builder

An ADU builder serving San Diego? Feature your business on this page.

Recent ADU permits in Southeastern San Diego

Street names only. See each permit on the map.

Questions about ADUs in Southeastern San Diego

How many ADUs have been permitted in Southeastern San Diego?

The City of San Diego issued 527 permits for ADUs in Southeastern San Diego from 2018 through Nov 4, 2026, including 107 garage conversions and 168 detached ADUs.

How long does an ADU permit take in Southeastern San Diego?

From application to issued permit, the median in Southeastern San Diego was 266 days for garage conversions and 256 days for detached ADUs.

How much does an ADU cost in Southeastern San Diego?

The median value declared on permits was $59,004 for garage conversions and $119,092 for detached ADUs. Declared permit values often understate the full construction cost, so get several builder quotes.

Can I build an ADU on my property in Southeastern San Diego?

California law allows ADUs on most residential lots with a house, but what you can build depends on your lot, zoning and hillside or fire-zone rules. This site shows permits, not eligibility; check with the City of San Diego Development Services Department or a licensed builder.