Public-record permit data only — not zoning, feasibility, or legal advice. Records may be incomplete, delayed, or mis-categorized. Check with your city planning department.
About this data
  • Neighborhood pages cover 2018 onward: City of San Diego Development Services Department permits located in this community planning area, the city's official neighborhood boundaries, which may not match every local definition of the neighborhood. Build type is classified automatically from permit descriptions.
  • Costs are declared permit valuations (single-ADU permits only), not final construction costs.
  • The city closes a permit both after its final inspection and after it expires, and its data doesn't say which, so this page doesn't estimate how many permits were finished. Closed permits stay in the counts.

Permits by year

201814
201921
202028
202157
202245
202385
202475
202595
2026 so far63
Permits by year and type (table)
YearAll ADU permitsGarage conversionsDetached
20181424
20192158
202028416
2021571521
2022451219
2023851233
2024751829
2025951639
2026 so far631318

“—” means the source for that year does not report ADU type.

Read more: ADU types explained

Not counted: 39 expired or cancelled permits.

How Mid-City Eastern Area compares

ADU rules

San Diego's ADU rules apply citywide, with extra rules in the Coastal Zone and in very high fire hazard areas: see the rules table.

How long permits take

TypeMedian days, application to permitMiddle halfPermits
Detached ADU237154 – 370187
Attached ADU214132 – 34546
Garage conversion186117 – 29497
Junior ADU (JADU)201116 – 31236
Unclassified267139 – 438116

Middle half: the range covering the middle 50% of permits (a quarter were lower, a quarter higher).

Read more: How long ADUs take to build

What neighbors declared as cost

TypeMedian declared valueMiddle halfPermits
Detached ADU$144,894$91,834 – $162,666156
Attached ADU$102,794$72,315 – $148,65542
Garage conversion$61,543$43,240 – $83,49889
Junior ADU (JADU)$45,083$38,888 – $58,46732
Unclassified$128,878$82,912 – $186,56171

Declared permit valuations often understate real construction cost.

Read more: How to choose an ADU builder

An ADU builder serving San Diego? Feature your business on this page.

Recent ADU permits in Mid-City Eastern Area

Street names only. See each permit on the map.

Questions about ADUs in Mid-City Eastern Area

How many ADUs have been permitted in Mid-City Eastern Area?

The City of San Diego issued 483 permits for ADUs in Mid-City Eastern Area from 2018 through Nov 4, 2026, including 97 garage conversions and 187 detached ADUs.

How long does an ADU permit take in Mid-City Eastern Area?

From application to issued permit, the median in Mid-City Eastern Area was 186 days for garage conversions and 237 days for detached ADUs.

How much does an ADU cost in Mid-City Eastern Area?

The median value declared on permits was $61,543 for garage conversions and $144,894 for detached ADUs. Declared permit values often understate the full construction cost, so get several builder quotes.

Can I build an ADU on my property in Mid-City Eastern Area?

California law allows ADUs on most residential lots with a house, but what you can build depends on your lot, zoning and hillside or fire-zone rules. This site shows permits, not eligibility; check with the City of San Diego Development Services Department or a licensed builder.

How current is this?

How our data works · Download the data · Free to reuse with credit to SoCal ADU Tracker (socaladutracker.com), under CC BY 4.0.