Public-record permit data only — not zoning, feasibility, or legal advice. Records may be incomplete, delayed, or mis-categorized. Check with your city planning department.
About this data
  • Neighborhood pages cover 2018 onward: City of San Diego Development Services Department permits located in this community planning area, the city's official neighborhood boundaries, which may not match every local definition of the neighborhood. Build type is classified automatically from permit descriptions.
  • Costs are declared permit valuations (single-ADU permits only), not final construction costs.
  • The city closes a permit both after its final inspection and after it expires, and its data doesn't say which, so this page doesn't estimate how many permits were finished. Closed permits stay in the counts.

Permits by year

20182
201919
202021
202124
202220
202350
202437
202546
2026 so far21
Permits by year and type (table)
YearAll ADU permitsGarage conversionsDetached
2018220
20191974
20202127
20212465
20222094
202350132
202437910
2025461310
2026 so far2124

“—” means the source for that year does not report ADU type.

Read more: ADU types explained

Not counted: 27 expired or cancelled permits.

How Otay Mesa-Nestor compares

ADU rules

San Diego's ADU rules apply citywide, with extra rules in the Coastal Zone and in very high fire hazard areas: see the rules table.

How long permits take

TypeMedian days, application to permitMiddle halfPermits
Detached ADU238145 – 36245
Attached ADU408179 – 40846
Garage conversion161104 – 29663
Junior ADU (JADU)16391 – 25936
Unclassified278209 – 45449

Middle half: the range covering the middle 50% of permits (a quarter were lower, a quarter higher).

Read more: How long ADUs take to build

What neighbors declared as cost

TypeMedian declared valueMiddle halfPermits
Detached ADU$101,556$73,640 – $144,99337
Attached ADU$72,564$56,351 – $100,34627
Garage conversion$53,148$40,764 – $77,36853
Junior ADU (JADU)$56,448$47,399 – $71,45036
Unclassified$77,287$45,122 – $116,31030

Declared permit valuations often understate real construction cost.

Read more: How to choose an ADU builder

An ADU builder serving San Diego? Feature your business on this page.

Recent ADU permits in Otay Mesa-Nestor

Street names only. See each permit on the map.

Questions about ADUs in Otay Mesa-Nestor

How many ADUs have been permitted in Otay Mesa-Nestor?

The City of San Diego issued 240 permits for ADUs in Otay Mesa-Nestor from 2018 through Nov 4, 2026, including 63 garage conversions and 46 detached ADUs.

How long does an ADU permit take in Otay Mesa-Nestor?

From application to issued permit, the median in Otay Mesa-Nestor was 161 days for garage conversions and 238 days for detached ADUs.

How much does an ADU cost in Otay Mesa-Nestor?

The median value declared on permits was $53,148 for garage conversions and $101,556 for detached ADUs. Declared permit values often understate the full construction cost, so get several builder quotes.

Can I build an ADU on my property in Otay Mesa-Nestor?

California law allows ADUs on most residential lots with a house, but what you can build depends on your lot, zoning and hillside or fire-zone rules. This site shows permits, not eligibility; check with the City of San Diego Development Services Department or a licensed builder.

How current is this?

How our data works · Download the data · Free to reuse with credit to SoCal ADU Tracker (socaladutracker.com), under CC BY 4.0.