Public-record permit data only — not zoning, feasibility, or legal advice. Records may be incomplete, delayed, or mis-categorized. Check with your city planning department.
About this data
  • Neighborhood pages cover 2020 onward: City of Los Angeles Department of Building and Safety permits in this neighborhood's Neighborhood Council area, which may not match every local definition of the neighborhood. Build type is classified automatically from permit descriptions.
  • Costs are declared permit valuations (single-ADU permits only), not final construction costs.

Permits by year

202056
202181
202296
2023101
202492
2025105
2026 so far84
Permits by year and type (table)
YearAll ADU permitsGarage conversionsDetached
2020562417
2021813233
2022963445
20231012744
2024922532
20251052138
2026 so far841331

“—” means the source for that year does not report ADU type.

Read more: ADU types explained

How Encino compares

ADU rules

Los Angeles' ADU rules apply citywide, with extra rules for hillside, fire-zone and coastal lots: see the rules table.

How long permits take

TypeMedian days, application to permitMiddle halfPermits
Detached ADU182119 – 304236
Attached ADU16089 – 328118
Garage conversion11153 – 221173
Junior ADU (JADU)7148 – 14855
Unclassified10641 – 23821

Middle half: the range covering the middle 50% of permits (a quarter were lower, a quarter higher).

Read more: How long ADU permits take in Los Angeles (and other cities) · How long ADUs take to build

What happened to these permits

Of the 334 ADU permits issued in Encino from 2020 through 2023, including ones that later expired or were cancelled, 77% have been signed off by the city as finished. Where the certificate of occupancy date is recorded, it came a median of 14 months after the permit.

What became of the permitShare
Finished (signed off by the city)77%
Still open22%
Expired or cancelled0%
Closed or other status1%

Expired and cancelled permits aren't in this page's totals; they're included here so the table covers every permit issued. A still-open permit may be under construction or stalled.

What neighbors declared as cost

TypeMedian declared valueMiddle halfPermits
Detached ADU$91,539$74,500 – $119,701232
Attached ADU$108,408$50,000 – $362,50064
Garage conversion$45,000$30,000 – $75,000171
Junior ADU (JADU)$30,000$20,000 – $50,00052
Unclassified$40,000$27,500 – $62,50019

Declared permit valuations often understate real construction cost.

Read more: What ADUs cost in Los Angeles

Read more: How to choose an ADU builder

An ADU builder serving Los Angeles? Feature your business on this page.

Recent ADU permits in Encino

Street names only. See each permit on the map.

Questions about ADUs in Encino

How many ADUs have been permitted in Encino?

The City of Los Angeles issued 615 permits for ADUs in Encino from 2020 through Oct 31, 2026, including 176 garage conversions and 240 detached ADUs.

How long does an ADU permit take in Encino?

From application to issued permit, the median in Encino was 111 days for garage conversions and 182 days for detached ADUs.

How much does an ADU cost in Encino?

The median value declared on permits was $45,000 for garage conversions and $91,539 for detached ADUs. Declared permit values often understate the full construction cost, so get several builder quotes.

How long does it take to build an ADU in Encino?

Of the 334 ADU permits issued in Encino from 2020 through 2023, including ones that later expired or were cancelled, 77% have been signed off by the city as finished. Where the certificate of occupancy date is recorded, it came a median of 14 months after the permit.

Can I build an ADU on my property in Encino?

California law allows ADUs on most residential lots with a house, but what you can build depends on your lot, zoning and hillside or fire-zone rules. This site shows permits, not eligibility; check with the Los Angeles Department of Building and Safety or a licensed builder.

How current is this?

How our data works · Download the data · Free to reuse with credit to SoCal ADU Tracker (socaladutracker.com), under CC BY 4.0.