The short answer

Of the 21,796 ADU permits the City of Los Angeles issued from 2020 through 2023, 82% have been signed off as finished, 1.4% expired or were cancelled, and 16% are still open: issued at least two years ago but not signed off. Few ADU projects fail outright; the ones that stall mostly stay open.

What became of each year's permits

Year issuedPermitsSigned offStill openExpired or cancelledClosed, other
20203,39086%12%1.0%0.4%
20215,09084%14%1.3%0.4%
20227,15081%17%1.8%0.5%
20236,16678%20%1.4%0.3%
20246,41472%28%0.1%0.2%
20256,95251%49%0.0%0.1%

Recent years are still being built, so a high “still open” share there is normal. The older years show which projects stalled. “Closed, other” covers every other status, such as closed without a final sign-off.

By neighborhood

Among the San Fernando Valley's Los Angeles neighborhoods, the largest shares of permits issued before 2024 still open are in Encino (22%), Pacoima (20%) and Canoga Park (20%); the smallest are in Sunland-Tujunga (10%), Valley Village (12%) and Lake Balboa (12%).

Approved, but never permitted

Some projects stall before the building permit. Across Ventura County, 1,080 ADU projects approved from 2018 through 2023 had no building permit reported by 2025. Over 2018–2025, the most are in Oxnard, Unincorporated Ventura County and Thousand Oaks. The state's reports only link an approval to its later permit when a city reports both the same way, so some of these may have been permitted under a separate record.

Why projects stall

Permit records show what happened, not why. They don't record a project's budget, financing, design changes or disputes, so this page doesn't guess at causes.

Keeping yours on track

Search your address on the map →

General information, not legal, zoning or financial advice. Rules change and depend on your lot; check with your city before you design or build.