About this data
  • Neighborhood pages cover 2018 onward: City of San Diego Development Services Department permits located in this community planning area, the city's official neighborhood boundaries, which may not match every local definition of the neighborhood. Build type is classified automatically from permit descriptions.
  • Costs are declared permit valuations (single-ADU permits only), not final construction costs.
  • The city closes a permit both after its final inspection and after it expires, and its data doesn't say which, so this page doesn't estimate how many permits were finished. Closed permits stay in the counts.

Permits by year

20187
201917
202017
202131
202216
202339
202427
202545
2026 so far35
Permits by year and type (table)
YearAll ADU permitsGarage conversionsDetached
2018714
20191765
20201737
202131710
20221624
2023391012
20242748
2025451416
2026 so far35813

“—” means the source for that year does not report ADU type.

Read more: ADU types explained

Not counted: 26 expired or cancelled permits.

How Navajo compares

ADU rules

San Diego's ADU rules apply citywide, with extra rules in the Coastal Zone and in very high fire hazard areas: see the rules table.

How long permits take

TypeMedian days, application to permitMiddle halfPermits
Detached ADU168100 – 30079
Attached ADU165115 – 26040
Garage conversion14677 – 24755
Junior ADU (JADU)12887 – 19017
Unclassified171116 – 24043

Middle half: the range covering the middle 50% of permits (a quarter were lower, a quarter higher).

Read more: How long ADUs take to build

What neighbors declared as cost

TypeMedian declared valueMiddle halfPermits
Detached ADU$84,209$65,075 – $114,81975
Attached ADU$83,396$64,462 – $148,91139
Garage conversion$60,182$39,743 – $74,67850
Junior ADU (JADU)$60,373$48,880 – $67,80817
Unclassified$87,225$66,965 – $110,04939

Declared permit valuations often understate real construction cost.

Read more: How to choose an ADU builder

An ADU builder serving San Diego? Feature your business on this page.

Recent ADU permits in Navajo

Street names only. See each permit on the map.

Questions about ADUs in Navajo

How many ADUs have been permitted in Navajo?

The City of San Diego issued 234 permits for ADUs in Navajo from 2018 through Nov 4, 2026, including 55 garage conversions and 79 detached ADUs.

How long does an ADU permit take in Navajo?

From application to issued permit, the median in Navajo was 146 days for garage conversions and 168 days for detached ADUs.

How much does an ADU cost in Navajo?

The median value declared on permits was $60,181 for garage conversions and $84,209 for detached ADUs. Declared permit values often understate the full construction cost, so get several builder quotes.

Can I build an ADU on my property in Navajo?

California law allows ADUs on most residential lots with a house, but what you can build depends on your lot, zoning and hillside or fire-zone rules. This site shows permits, not eligibility; check with the City of San Diego Development Services Department or a licensed builder.

How current is this?

How our data works · Download the data · Free to reuse with credit to SoCal ADU Tracker (socaladutracker.com), under CC BY 4.0.